Rules and compliance
16. Permits for a sagra (food festival) in Italy: procedures, deadlines and sources
The one-stop shop, show licences, safety approval, fire brigade, food, the 118 service, police and public land: what Italian law says, with links to the texts
In this article
- Why there is no fixed number of permits
- 1. Where to start: the municipality's one-stop shop (SUAP)
- 2. Is there a show? Licence or SCIA
- 3. Stages, stands and barriers: safety approval and the inspection commission
- 4. The fire brigade: no "advance notice", but two routes
- 5. Food and drink: SCIA and hygiene rules
- 6. First aid: notifying the 118 emergency service
- 7. Police and public order
- 8. Squares and streets: public land and traffic
- 9. Music and tickets: SIAE
- 10. Insurance and volunteers
- Two worked examples
- Common mistakes
- How Play the Event fits in
- Checklist
- Sources
Updated on 1 October 2026 - by the Play the Event editorial team. The laws and documents quoted here were read on 1 October 2026: check that they have not changed before relying on them.
This guide has been rewritten. The previous version described procedures that do not exist, such as a SUAP application requiring a passport and a CV, a fire brigade notice due 90 days ahead, a health declaration due 30 days ahead and fixed police thresholds. We removed them: every rule below links to the text it comes from.
Important notice. This guide is about food festivals and village fairs (in Italian, sagre) held in Italy. It is general guidance, not legal advice. Forms, deadlines and offices change from one municipality and region to another, and most of the official sources are available in Italian only. The final answer for your event comes from the municipality's one-stop shop and, where needed, a licensed engineer or surveyor. If you are organising in another country, the questions are the same (venue, safety, food, music, first aid), but the offices, names and deadlines differ: start with your local council's events office.
Why there is no fixed number of permits
Italy has no single national list of "permits for a sagra". What you need depends on what you plan to do: serve food and drink, put on a show, build a stage or stands, use a public square, how many people you expect and how late you finish. A cake stall in a courtyard and a three-day festival with a concert in the main square need very different paperwork. So this guide is organised by question: for each one you get the rule, a link to the text and the office in charge.
1. Where to start: the municipality's one-stop shop (SUAP)
The SUAP (Sportello unico per le attività produttive, one-stop shop for business activities) is an office of the municipality, or of several municipalities together, set up under Presidential Decree 160 of 7 September 2010. It is not a permit in itself: it is the channel for applications and notifications about business activities, including many of those for temporary events. Depending on the municipality, the online portal is impresainungiorno.gov.it or a municipal or regional one; you usually log in with an Italian digital identity (SPID, CIE or CNS).
The most useful first step is to write to the SUAP with a short description of the event (dates, times, place, what will happen, expected attendance) and ask which procedures apply and how far in advance. The questions it will ask you are the ones in the sections below.
2. Is there a show? Licence or SCIA
Article 68 of the Consolidated Public Security Act (TULPS) requires a licence to hold dances "or other similar shows or entertainments" in a public place or a place open to the public. The 1931 text says the licence comes from the Questore (the provincial police chief), but Article 19 of Presidential Decree 616 of 24 July 1977 moved this power to municipalities: you apply to the municipality, usually through the SUAP.
Article 68 also has a simplified route: for events with up to 200 participants that take place by midnight of the day they start, the licence is replaced by a SCIA (segnalazione certificata di inizio attività, a certified notice that the activity is starting) filed with the one-stop shop. Both conditions apply: on the wording of the law, an evening with 150 people that ends at 1 a.m. does not qualify.
Not all music at a sagra counts as a "show" in this sense. The guide published by the Prefecture of Bergamo for organisers, for example, says the provincial commission is not involved when occasional music is played in a space whose main activity is serving food and the music is only an extra (Prefecture of Bergamo, operating guide, chapter III). That is one prefecture's reading, not a national rule: ask your municipality how it classifies your programme.
3. Stages, stands and barriers: safety approval and the inspection commission
For places of public entertainment, Article 80 of the TULPS requires a technical commission to check structural soundness, safety and exits before the licence is issued. The TULPS implementing regulation (Royal Decree 635 of 6 May 1940, Articles 141, 141-bis and 142, rewritten by Article 4 of Presidential Decree 311 of 28 May 2001) sets out three cases:
| Capacity of the venue or facility | Who checks it |
|---|---|
| up to 200 people | instead of the commission, a technical report signed by a registered professional is enough, without prejudice to health rules |
| over 200 and up to 5,000 people | the municipal inspection commission |
| over 5,000 people | the provincial inspection commission, at the Prefecture |
For cinemas, theatres and travelling shows the provincial threshold is lower: over 1,300 spectators.
The municipal commission includes, among others, the provincial fire brigade commander or a delegate and the senior doctor of the local health authority (ASL) or a delegated doctor (Article 141-bis). This is one of the places where the fire brigade and the health authority review your plans.
If your sagra comes back every year. Temporary set-ups that are repeated periodically do not need a new inspection if the commission granted approval no more than two years earlier, unless the nature of the site calls for a new check (Article 141 of the regulation).
How far ahead. There is no single national deadline: the commission's own rules set it. The Prefecture of Bergamo asks for applications for temporary events at least 20 days in advance, and the model municipal regulation attached to its guide sets 30 days for temporary events, sagre included (same source, chapter IV and annexes). If your municipality's commission meets rarely, the real lead time is longer: ask for its meeting calendar.
4. The fire brigade: no "advance notice", but two routes
There is no notice to the fire brigade (Vigili del fuoco) to be sent 90 days in advance. The fire brigade gets involved in two ways:
- through the inspection commission, when your event needs one (section 3);
- through fire prevention rules under Presidential Decree 151 of 1 August 2011, if you use a venue or facility that falls within them. Activity no. 65 of Annex I covers entertainment venues with a capacity above 100 people or an indoor gross floor area above 200 m², and adds: "Temporary events of any kind held in premises or places open to the public are excluded".
If the kitchens will run on LPG cylinders, the Bergamo guide points to the Ministry of the Interior circular no. 3794 of 12 March 2014, with fire prevention technical guidance for markets on public land (operating guide, chapter III). Ask the provincial fire brigade command, or the professional signing your report, how it applies to your set-up.
5. Food and drink: SCIA and hygiene rules
Temporary food and drink service "on the occasion of sagre, fairs, religious, traditional and cultural events or exceptional local events" starts with a SCIA, with no sworn technical statements and without the professional requirements that apply to ordinary food businesses (Article 41 of Decree-Law 5 of 9 February 2012).
The hygiene framework is EU Regulation (EC) No 852/2004, whose Article 6 requires food business operators to notify the competent authority of each establishment under their control, for registration. In Italy there is no single national form and no national 30-day deadline for a "health declaration": how this applies to a temporary stall, which form to use and how far ahead are set by the region and the local health authority. In some municipalities the notification is attached to the SUAP application, in others it is separate: ask the one-stop shop before you settle the menu and the equipment.
6. First aid: notifying the 118 emergency service
An agreement adopted by Italy's Unified Conference of State, regions and local authorities on 5 August 2014 (ref. no. 91/CU) sets guidelines for medical cover at planned events, and each region adopts it with its own act. Lombardy, for example, with Regional Council Resolution X/2453 of 7 October 2014, asks organisers to work out a risk level using a table and to notify the 118 emergency service with a lead time that grows with the risk:
| Risk level (Lombardy) | Notice to the 118 service |
|---|---|
| very low or low | at least 15 days before the start |
| moderate or high | at least 30 days before the start |
| very high | at least 45 days before the start |
Other regions may set different deadlines and forms: look on the website of your regional 118 service or local health authority for the page on events. The number of first-aiders, ambulances and first-aid posts is not a guess: the medical plan derives it from the risk level.
7. Police and public order
Article 18 of the TULPS requires the promoters of a gathering in a public place, or a place open to the public, to notify the Questore at least three days in advance. The Bergamo guide says that the organiser of a public entertainment event notifies the Questore and attaches a copy of that notice to the licence application filed with the SUAP (operating guide, summary note). Three days is the legal minimum: if safety needs to be assessed, start much earlier.
For both "safety" (protecting people) and "security" (public order), the reference is the Ministry of the Interior directive no. 11001/1/110/(10) of 18 July 2018, which the Bergamo guide reproduces in an annex. If the commission finds that an event raises particular concerns it informs the Prefecture, which can refer it to the provincial committee for public order and security (same source). There is no national headcount above which an event must be "registered" with the police, and no fixed ratio of staff per square metre: capacity, escape routes and staffing come from the plan and from the authorities' requirements.
8. Squares and streets: public land and traffic
If the sagra uses a square, a street or a municipal park, you need a permit to occupy public land, subject to the single property levy under Article 1(816) et seq. of Law 160 of 27 December 2019 and to your municipality's regulation, which sets the rates and any reductions. Road closures and parking bans are requested from the municipality, usually from the local police.
9. Music and tickets: SIAE
If you use protected music you need a copyright licence, even when entry is free: rates and sources are in Music and copyright: SIAE licences for your event in Italy. For tickets and the related obligations, see Tickets and SIAE in Italy: when an event is subject to the rules and how to sell tickets.
10. Insurance and volunteers
The municipality, the landowner or the public land rules may require third-party liability insurance. Even when it is not required, talk to an insurer about cover for injury and damage. If you are a registered third-sector organisation working with volunteers, Article 18 of the Third Sector Code (Legislative Decree 117 of 3 July 2017) requires you to insure them against accidents and illness linked to the activity, and for third-party liability.
Two worked examples
These examples show the reasoning; they do not replace your municipality's answers. Deadlines marked "municipality's" are assumptions made for the example.
Example A: a Saturday in the square, 150 people, ends at 11:30 p.m.
A local association runs a sagra from 6 p.m. to 11:30 p.m., with an electric-hob kitchen, a band on a low platform and 150 people expected in a fenced area.
- Show: under 200 participants and finishing before midnight, so a SCIA instead of a licence (Article 68 TULPS).
- Safety approval: capacity up to 200 people, so a professional's technical report instead of the commission (Article 141 of the regulation).
- Food: SCIA for temporary food service (Article 41 of Decree-Law 5/2012) and food registration under the regional rules.
- Public land: permit and levy under the municipal regulation.
- 118: if the event were in Lombardy and the table gave a low risk, notice at least 15 days ahead.
- Police: notice at least 3 days ahead, if the municipality or the Questura consider it due.
Countdown for this example: 60 days before, contact the SUAP and hire the professional; 45 days before, apply for public land (municipality's deadline); 30 days before, SCIA, technical report and food registration (municipality's deadline); 15 days before, notify the 118 service; the week before, notify the Questore, leaving margin over the 3 days.
Example B: a concert in the square, 2,000 people, ends at 1 a.m.
- Over 200 people and finishing after midnight: a licence is needed, not a SCIA.
- Capacity between 200 and 5,000 people in a place other than a cinema or theatre: municipal inspection commission, with the deadlines in its rules (30 days in the model attached to the Bergamo guide).
- Notice to the 118 service according to the risk level: in Lombardy at least 30 days ahead if the risk comes out moderate or high.
- A safety plan following the directive of 18 July 2018, and a possible review at the Prefecture.
Common mistakes
- Trusting deadlines found online with no source: the real ones are in the law or in your municipality's regulation.
- Counting on the 200-person SCIA when the evening runs past midnight.
- Assuming "free entry" means no permits: music and food have their own procedures.
- Building platforms and stands without asking whether a technical report or the commission is needed.
- Finding out the commission's meeting calendar two weeks before the event.
- Leaving medical cover to the end: in some regions the 118 service must be notified weeks ahead.
How Play the Event fits in
Play the Event does not file any applications for you and does not replace the SUAP, the inspection commission or a licensed professional. You can use it to organise the rest of the event and to add each procedure to your task list with its deadline, so the countdown stays under control.
Checklist
- When, where, until what time and for how many people?
- Is there a show, or only background music while people eat?
- Will you build stages, platforms, stands or barriers?
- Will you serve food and drink? With what equipment, LPG included?
- Will you use public land or close streets?
- What is the medical risk level, and how far ahead must the 118 service be notified in your region?
- Have you asked the SUAP for your municipality's deadlines and the commission's calendar?
- Protected music: do you have a licence from SIAE or whoever manages the repertoire?
- Insurance and, for third-sector organisations, volunteer cover?
Sources
All consulted on 1 October 2026. Most are in Italian.
- Presidential Decree 160 of 7 September 2010, regulation on the one-stop shop for business activities - Normattiva, 2010.
- Royal Decree 773 of 18 June 1931 (TULPS), Articles 18, 68 and 80 - Normattiva, current text.
- Presidential Decree 616 of 24 July 1977, Article 19 - Normattiva, 1977.
- Royal Decree 635 of 6 May 1940, TULPS implementing regulation, Articles 141, 141-bis and 142 - Normattiva, current text.
- Presidential Decree 311 of 28 May 2001, Article 4 - Gazzetta Ufficiale, 2001.
- Presidential Decree 151 of 1 August 2011, fire prevention regulation, Annex I - Normattiva, 2011.
- Decree-Law 5 of 9 February 2012, Article 41 - Normattiva, 2012.
- Regulation (EC) No 852/2004 on the hygiene of foodstuffs, Article 6 - EUR-Lex, 2004.
- Lombardy Region, Resolution X/2453 of 7 October 2014, medical cover at planned events - AREU Lombardia, 2014.
- Law 160 of 27 December 2019, Article 1(816) et seq. - Normattiva, 2019.
- Legislative Decree 117 of 3 July 2017 (Third Sector Code), Article 18 - Normattiva, 2017.
- Prefecture of Bergamo, operating guide to public entertainment events for public and private organisers - Ministry of the Interior, file published in March 2023.
Frequently asked questions
What permits do you need to run a sagra in Italy?
It depends on what you plan to do. The usual procedures cover the show (licence or SCIA under Article 68 TULPS), safety approval for stages and stands (inspection commission or technical report), food service (SCIA under Article 41 of Decree-Law 5/2012 and food registration), public land, medical cover and music (SIAE). Start by asking your municipality's SUAP.
Do you have to send a health declaration to the ASL 30 days ahead?
There is no national rule like that. Regulation (EC) No 852/2004 requires food establishments to be notified to the competent authority; the form, channel and lead time for a temporary stall are set by the region and the local health authority. Ask the SUAP.
When is a SCIA enough instead of a show licence?
Under Article 68 of the TULPS, when the event has up to 200 participants and takes place by midnight of the day it starts. Both conditions must be met.
How far ahead must the police be notified?
Article 18 of the TULPS requires notice to the Questore at least three days before a gathering in a public place or a place open to the public. That is a minimum: if safety needs to be assessed, start much earlier.
Does Play the Event file the applications for me?
No. Play the Event does not file applications and does not replace the SUAP or a licensed professional. You can use it to organise the event and keep track of each procedure's deadline in your task list.
Put it into practice
Free tools for this guide
- Free tool
Event Risk Assessment Tool with Risk Matrix
Build a risk matrix for your event: probability and impact for each risk, with preventive actions and contingency plans.
- Free tool
Event Planning Checklist Generator
Generate an event planning checklist by event type and size, with tasks grouped into four phases: research, planning, on site and after the event.
Article 16 of 46